FY 2012 Homeland Security Grant Program
(HSGP) Timeline
(Updated as of: 11/08/12) |
| JUN 01 2012 |
Eligibility Instructions sent out by SAA. |
| JUN 22 2012 |
Regions and UASIs start to enter projects in SPARS. |
| JUL 02 2012 |
Deadline for Applicants to Submit Eligibility Certification Forms. |
| JUL 20 2012 |
Deadline for Regions and UASIs to have all projects (without distribution information)
submitted in SPARS for review. |
| AUG 10 2012 |
Target Date for SAA to have all Eligibility Certification Forms fully processed and recorded in SPARS. |
| AUG 10 2012 |
Regions and UASIs begin entering distribution information. |
| SEP 7 2012 |
Deadline for Regions and UASIs to have all projects submitted with distributions in SPARS. (Note: SAA may delay final approval step (generation of SRA) until federal award is received and SAA has reviewed and approved all projects.) |
| SEP 11 2012 |
State received 2012 HSGP award from DHS. |
| OCT 01 2012 |
Date the SAA issued and emailed 2012 HSGP sub-recipient agreements
(Completed this prior to 45 day requirement by DHS).
|
| NOV 15 2012 |
Deadline for signed sub-recipient agreements to be returned to SAA (45 days from
SAA award). |
| NOV 30 2012 |
Deadline for sub-recipient to have entered their initial BSIR data in SPARS and obtain SAA approval (45 days from SAA award). |
| DEC 14 2012 |
Deadline for sub-recipient to enter Project Milestones for Approved 2012 Projects. (*Sub-recipients shall enter Milestones in SPARS within 14 days after grant acceptance is “completed” in SPARS by the SAA.) |
| FEB 28 2013 |
Deadline for sub-recipient to submit 2012 project EHP Screening Forms to the SAA. |
JAN 31 2014
Local = 17 Months
COGs = 20 Months
UASI Core Cities = 21 Months
|
Anticipated Sub-recipient Performance Period End Date*.
*All invoices have been entered into SPARS.
COGs would have a Performance Period end date of April 30, 2014, and UASI Core Cities would have a Performance Period end date of May 30, 2014. |